Back to inventory2 orders
Open In transit Open Receiving7 transactions
Receiving preview — see this SKU before and after PO-2024-089 is received
SS-2FLG-L150Stockout RiskStainless Steel
2" 150# 316SS Flange
Slip-on flange · 150# pressure rating · stocked in EA · Location A-04-1 · $54.00 / EA
- Material
- 316 SS
- Size
- 2"
- Type
- Flange
Available
3EA
Bench Level
15EA
Velocity
0.7EA/day
Days Remaining
4days
Lead Time
90days
Incoming
25EA
On Hand 8 EAAllocated 5 EASafety buffer 14 daysLocation A-04-1
On Hand (8) is below Bench Level (15)BO-0087 awaiting receipt
Decision support
Replenishment Outlook
Usage window
Stockout RiskStockout Risk
At the current usage rate, inventory is projected to fall below the 15-unit bench level on Aug 20, 2026 (0 days). Supplier replenishment requires approximately 90 days. Existing incoming inventory is not sufficient to prevent a projected shortage.
Recommended order
65 EA
Average usage
0.7EA/day
30-day usage
21EA
60-day usage
39EA
90-day usage
54EA
Days of supply
4days
Supplier lead time
90days
Safety buffer
14days
Incoming inventory
25EA
Expected arrival
Aug 18, 2026PO-2024-089
Projected inventory at replenishment
-35EA
Projected shortage
50EA
Recommended order quantity
65EA
Available ÷ 0.7/day = 4 days of supply · compared against lead time 90d + buffer 14d = 104d cover required
Usage · last 90 days
Increasing 12%12 wks agoThis week
Velocity trend: Increasing 12% over the trailing 90 days.
Demand allocation
Current Allocations
| Order # | Customer | Qty Allocated | Status | Required date |
|---|---|---|---|---|
| SO-2024-0142 Line 2 | Midwest Mechanical | 5 EA | Partial | Aug 19, 2026 |
| SO-2024-0139 Line 1 | Apex Mechanical Contractors | 3 EA | Allocated | Aug 14, 2026 |
Open demand
Backorder / Open Demand
10EA
PO-2024-089Supply pipeline
Incoming Inventory
25EA
10 EA earmarked for BO-0087
Audit trail
Transaction History
| Date / time | Type | Reference | Qty | Balance |
|---|---|---|---|---|
| Aug 4, 2026 2:22 PM | Allocation | SO-2024-0142 Partial allocation — 5 of 15 available | -5 | 8 |
| Aug 4, 2026 2:22 PM | Backorder | SO-2024-0142 / BO-0087 Backorder created for remaining 10 units | -10 | 8 |
| Aug 3, 2026 11:15 AM | Allocation | SO-2024-0139 Allocated to Apex Mechanical Contractors | -3 | 13 |
| Aug 2, 2026 9:30 AM | Receipt | PO-2024-082 Received from Pacific Fittings Supply | +30 | 16 |
| Jul 28, 2026 3:45 PM | Sale | SO-2024-0131 Shipped to Harbor Industries LLC | -8 | 14 |
| Jul 25, 2026 10:00 AM | Adjustment | ADJ-0023 Physical count correction | +2 | 6 |
| Jul 20, 2026 8:00 AM | Receipt | PO-2024-076 Received from Pacific Fittings Supply | +25 | 8 |